Sam Schwartz Engineering recently released a schedule for Second Avenue Subway construction slated to take place through Jan. 31.
From 100th to 96th streets, crews will work on sewer relocation and cap existing gas lines on the west side of the street. They will also establish a new storage zone and one crew will shift to the south side of 96th Street for water main work. Read more
Subway Construction Updates
Traffic pattern shifts between East 91st and 100th streets
By Reid Spagna
Sam Schwartz Engineering recently released a construction schedule, which outlines work to be completed on the Second Avenue Subway through July 19. Read more
Subway Construction Updates
Blasting focus between East 69th and 70th streets
Sam Schwartz engineering recently released a schedule for Second Avenue subway construction through June 28. Read more
2nd Ave. Subway Construction Updates
Sam Schwartz Engineering recently released a schedule for Second Avenue subway construction through April 19.
Work on the 96th Street Station will span East 95th to 100th streets. Workers will install a Con Edison duct bank and a manhole at East 99th Street, and restore sections of pavement and sidewalk. Between East 97th and 99th streets, projects include the installation of a 12-inch water main, backfilling a sewer trench and excavating a storm drain and a 30-inch gas main. Read more
Subway Construction Updates
Sam Schwartz Engineering released a Second Avenue subway construction schedule through Dec. 13.
In the section spanning East 95th to 100th streets, construction work is slated to include Con Edison projects, as well as sewer, utility and gas main relocation, and the demolition of the Century Lumber building at 1875 Second Ave., between East 96th and 97th streets.
Between East 93rd and 95th streets, workers will continue soil excavation of the launch box and the installation of wales and struts. Read more